In 1975 the Hubbard Lake Substation was constructed.
In 1976 the Abitibi (now DPI) Substation was constructed to serve the increased load at the plant.
In 1978 the Norway Substation was constructed.
In 1979 the Bagley Street Substation was constructed.
In 1980 the Rockport Substation was constructed.
Also in 1980, the first Energy Thrift Note (similar to a certificate of deposit) was issued. APC was one of two utilities in the U.S. to offer such notes to their customers.
In 1980 APC had about 13,500 customers.
In 1985 APC donates 6,600 acres in the Fletcher Pond area to the Thunder Bay Audubon Society. The pond has the largest Osprey population east of the Mississippi River.
In 1986 the Potter Field Substation was constructed. This increased APC's energy capacity to 158 megawatts.
In 1989, a mural depicting APC's history was painted on APC's main office building by a local artist.
On August 31, 1990, all hydro electric generation power plants and associated lands and facilities were sold to Thunder Bay Power Company. These included Ninth Street Dam, Four Mile Dam, Norway Point Dam, Hillman Dam, Hubbard Lake Reservoir Dam and Upper South Reservoir Dam.
In 1990 APC had about 13,900 customers.
In 1993 the Progress Street Substation was constructed to improve power quality and reliability for APC's customers in Hillman. This increased APC's energy capacity to 170 megawatts.
Also in 1993, the North Side rebuild project, which converted the existing 4,160 volt system to 13,200 volts, was completed. The project was started in 1986 and cost more than $1,000,000. The Long Lake Substation was decommissioned as part of the project.
In 1994 APC entered into a 30 year agreement to purchase power from Consumers Power Company (now Consumers Energy).
In 1996 the Central Substation was constructed to eventually replace the lower voltage Ninth Street Substation.
Between 1996 and 2004 capacity is increased at eight substations to enable APC to serve its customers' growing demand for electricity.
In 1999 the North Industrial Substation was constructed.
In 2000 the M-32 Substation was constructed.
In 2000 APC had about 15,400 customers.
In 2001, the South Side rebuild project, which converted the existing 4,160 volt system to 13,200 volts, was completed. The project was started in 1995 and cost more than $1,700,000.
2003 - 2005: APC's energy capacity was increased to 202 megawatts when transformer upgrades were completed at Gennrich, Four Mile and Potter Field Substations.
In November 2006 APC's Ninth Avenue garage was renovated to provide additional office space. All employees now are located at that facility.
In 2007 APC had about 16,300 customers. |