New service is identified as the actual installation of new electrical equipment. It does not represent new or existing customers relocating to established APC service locations.

Commercial or Industrial Overhead Service

With exception of the charges required for new underground service, APC will finance the construction cost necessary to extend its overhead facilities to serve commercial or industrial customers when such investment does not exceed two times the estimated annual distribution revenue anticipated to be collected from customers initially served by the extension. When said costs do exceed the revenue anticipated, customers shall be required to pay the additional costs associated with the extension. Certain categorical limits apply. Our Engineering Department will be happy to schedule you with the necessary APC staff to begin this process. Please call 989.358.4955.